April 10, 2008
After some beaucratic delays, Alto Construction Ltd, will start interviews with the 34 Ground Floor Life Leases on Monday, April 14, 2008. Mobilization is underway. Building Permits are being issued by the City of Castlegar, on April 11, 2008
The Building Committee is pleased to announce the appointment of Cyril Sookachoff as Clerk of Works starting immediately. His function is to coordinate the construction of the Ground Floor Life Leases and ensure that the work by Alto Construction Ltd meets the expectations of the members.
Scheduled "Pick Dates"
- April 12, 2008
- April 26, 2008
- May 10, 2008
- May 24, 2008
- June 07, 2008
- June 21, 2008
Sequencing of Construction of Ground Floor Units
With a construction start on the first 34 units, the construction scheduling will be such that all new commitments will follow the first 34 committed members.
Future sequencing will start at D30 and flow to the South West to the end at D17 along Grandview Drive to 14th Avenue. It is anticipated that the Triplexes will be the last to be constructed.
The Bungalows will flow from B19, West along Calemeda to 14th Avenue
Other locations for selections are possible; however, construction will not take place until the sequence is complete prior to the selected unit.
Note that contractor's pricing may be affected to future selections so the sooner selections are made the less impact on prices will take place.
Scheduled General Meetings
- Meeting 4100, April 20, 2008
- Meeting 4200, May 25, 2008
- Meeting 4300, June 22, 2008
Site Ceremony Saturday, April 19, 2008 at 1000 hours
Please come out and celebrate the start of construction on the Ground Floor Units and wear your Grandview Heights T-shirts.