May 23, 2008
Contracts
- Selkirk Paving Ltd
- Letter of intent to be issued May 02, 2008.
- Alto Construction Ltd
- After costs are established with 2nd Interview then total contract amount will be established
- Contract documents all printed an ready
- CCDC document 14 needs to be completed with costs
- Temporary Overhead Power
- A Letter of Intent has been issued to Martech Electrical Systems Ltd
- Fortis BC is evaluating their power line at Sahstrom property and suggest that a $75,000 upgrade may be necessary
- Martech has huge Genset and cables available and will meet the budget in the end
- More later
- U/G Electrical. Telus, Shaw
- Letter of Intent issued to Maretech Electrical Systems Ltd
- Installation to start May 05, 2008 and completed June 30, 2008
- Telus approval had tendency to holdup but now on track
Ground Floor Housing
- Status of Financial Commitment Letters
- GFLLs agreed to make 2nd contractual deposit May 25, 2008.
- ACL Construction Status
- Work continues and 1st framing should be visible week of May 26, 2008.
- Some changes being priced:
- Driveways
- Excavation and Backfill
- Deletion of Peremeter Drainage
- Change crawlspace floor concrete strength from 25 Mpa to 20 Mpa
- A 2 meter long concrete apron at garage door
Next Pick Dates
- May 24, 2008
- June 07, 2008.
- June 21, 2008.
Heritage Credit Union
- Construction Account for GFLLs is set up
- “Bridge Financing” confirmed and activated
- Application for Letter of Credit to City of Castlegar for Infrastructure Maintenance being made May 22, 2008.
Appraisal with Strand Godfrey
- Will be made available for inspection by members at Meeting 4200
Infrastructure Construction
- MiL is completing various tie-ins over the bank
- Waiting to do gutters and sidewalks ASA U/G power is in
Countdown to Registration of Subdivision for Phase I
- Set for June 30, 2008 survey plan approval by City of Castlegar
- Legal registration of easements required
- Letter of Credit for Infrastructure Maintenance required
- List of requirements received from Phil Markin Approving Officer
- Park allocation negotiation underway
Emerald Green Developments
- Final Construction Permit from CoC still O/S
Should you have any questions do not hesitate to contact Elmer or one of the Directors?.
Elmer Verigin, Project Manager
KCSHC