Click here for a larger view of the Site Plan, last revised July 28 2009.

Call for Tenders
The Grandview Manor project is moving toward construction phase. The Call for Tenders that went out in January is now closed.
- Five (5) Design / Build Proposals were received February 18th, 2010.
- Selection review is underway for three (3) Proponents to conduct a Post Tender Addendum for a final Tender Price.
- April 09, 2010 - The three contractors retained for the Post Tender Addendum are:
- Tri-City Contracting (BC) Ltd
- Maple Reinders Inc.
- Vic Van Isle Construction Ltd
* July 19, 2010 - A Conditional Letter of Intent was signed with Tri-City Contracting (BC) Ltd
This plan of the area shows the location of the various housing units, the care centre and the additional free hold lots for sale.
- Grandview Heights
Phase I saw the completion of the bungalows and duplexes along the edge of the bank (34 units). Virtually all these units have a spectacular view of the Columbia River to the east and south. Our members moved into their new homes in the spring of 2009.
- Phase II is currently underway. Construction of duplexes and bungalows has started on the opposite side of Grandview Drive for occupancy in the early part of 2010. See the Homes Available page for current information about what units are still available.
Watch our Progress
August 12, 2006 (click image to zoom):
November 13, 2006 (click image to zoom):
June 14, 2007 (click image to zoom):
April 12, 2010